University of Tennessee Board of Trustees approved a budget increase for Neyland Stadium renovations on Friday.
The increase in budget for phase 1 of Neyland Stadium’s renovation project is from $49 million to $337 million.
A timeline of renovations was announced by Tennessee in a press release and is listed below.
Fall 2023
- Removal of South Stadium Hall with structural strengthening of the stadium’s south end
- Partially completed Wi-Fi capabilities
- Brick cladding around in-bowl vomitories
- New restrooms under the Gate 10 ramp
Fall 2024
- Full stadium-wide Wi-Fi connectivity
Stadium kitchen, commissary and loading dock - New southeast elevators vertically connecting all concourses
- New Gate 4 entry plaza
- Brick cladding around in-bowl vomitories (phase 2)
- Renovations and upgrades complete for all stadium skyboxes (see updated renderings)
- Initial construction for the westside Founders Suites New restrooms and concessions on north concourse two
Fall 2025
- Expanded south concourse 1 (increased restrooms, enhanced concessions, wider concourse)
- Completed Founders Suites
- Tee Martin Drive to shift south of the Gate 10 ramp
Fall 2026
- Completion of entry plazas
[affiliatewidget_smgtolocal]